Roadwork and Maintenance closures

CITY OF MARYSVILLE PROJECTS 

New Traffic Circles on 2nd Street

Beginning Wednesday,April 18th, City crews will be installing three (3) traffic circles located along 2nd Street at the intersections of Alder, Quinn and Union avenues. This work is weather dependent but the project is expected to be completed by the end of April.



Construction starts early April on new Marysville water main.


Work to build a new water main along Sunnyside Boulevard Northeast is began April 9. Construction of the 537-linear-foot project will start at Soper Hill Road and extend north to 29th Place Northeast. It includes building a new water main and services in the northbound lane of Sunnyside Boulevard Northeast. The project is expected to be complete in May. Residents and travelers on Sunnyside Boulevard Northeast can expect single-lane closures with flaggers and potential delays.

This $141,671 project was included in the city’s 2017-18 biennial budget. Contractor SRV Construction, Inc. is performing the work.

WSDOT Projects:

NB Steamboat Slough Bridge Painting - #9043

Highway: SR 529    Region: Northwest    County: Snohomish    Location: Milepost(s) 5.42 - 5.71
Contact: Mark Sawyer, Project Engineer, 425-225-8799
Description: WSDOT contractor crews are cleaning and painting the northbound SR 529 Steamboat Slough Bridge between Everett and Marysville.
Project webpage
Work schedule:
 
Monday, April 16, to the morning of Friday, April 20 - A single lane on the northbound SR 529 Steamboat Slough Bridge will be closed from 7 p.m. to 1 a.m. nightly.   
 

 

Updated April 17, 2018